Description
Practices and procedures to identify potential sources of sediment to reduce sediment discharge from construction sites.
Applications
- Any potential source of sediment on all projects.
Installation and Implementation Requirements
- Configure construction site to ensure vegetated areas buffer haul roads, stockpiles, and adjacent waterbodies. Vegetation provides an effective means of reducing sediment and pollutants discharged off-site.
- Place stockpiles away from waterways, drains and low spots.
- Direct off-site runoff away from bare ground.
- Maintain vegetation in swales and natural drainage ways.
- Designate naturally level areas for parking and equipment staging during construction.
- Inspect the construction site during or immediately following a rain event to identify the storm water’s natural path to locate where sediment leaves the site. This will assist in Storm Water Pollution Prevention Plan (SWPPP) design and BMP placement.
What to Inspect
- Where are the exposed areas on the construction site?
- Is there evidence of run-on and/or runoff?
Maintenance
- Install, repair, or replace BMPs to cover exposed areas or redirect off-site runoff.